Port-Of-Hastings-Main000.jpg

News

29/08/2018 - Subsea7 Works Have Commenced

Subsea 7 have commenced works at the Port of Hasting’s Crib Point Jetty. The site is currently being set up with site sheds and a barge has arrived to undertake works to accommodate the Cooper Sole pipe spooling project. The Port of Hastings requires that parties undertaking works at the Port receive the relevant regulatory approvals prior to works proceeding. In this case, the project has received approval under the Coastal Management Act for the installation of berthing dolphins and pipe rollers.

This Project last occurred at the Port in 2009. The Project will involve spooling 64km of 12” pipeline for installation offshore in the Gippsland Basin as part of the Sole Development Project. Spooling operations are scheduled to commence in September and can be viewed by the public from the Wooleys Beach reserve. Residents can expect to see increased activity at the Crib Point Jetty site from now until the end of the year.

 Pipe Spooling Operations at Crib Point in 2009

Pipe Spooling Operations at Crib Point in 2009

 

If you have any queries please contact the Port of Hastings or visit the Subsea7 website at:  http://www.subsea7.com

 

 

 

 

 

 

 

 


 

21/06/2018 - Coastal Management Act Consent

The Port of Hastings Development Authority has received consent for use and development of coastal Crown land from the Department of Environment, Land, Water and Planning to commence work remediating Crib Point Berth No.2.

Please click on link below to download pdf version of the documents

Crib Point Jetty Upgrade Project - Coastal Management Act Consent

Crib Point Jetty Upgrade Project - Condition 2 Consent

Environmental Management Plan

Environmental Risk Assessment

Stakeholder Management Plan


 

12/06/2018 - AGL Announcement

Today AGL and the Port of Hastings Development Authority (the Port) entered into an agreement that will soon see the Port commence work remediating Crib Point Berth No.2 (the Berth).

Port of Hastings CEO Malcolm Geier is looking forward to working with AGL as work on the project approvals and feasibility studies continue.

“The Port team and myself look forward to working with AGL and the community on the next phase of what is an exciting project for the Port and Crib Point.”

The project requires a floating storage and regasification unit (FSRU) to be continuously moored at Crib Point Berth No.2. “The agreement signed today will enable the Port to commence work remediating Berth 2 at Crib Point ahead of a final investment decision being made by AGL in the 2019 financial year.”

“The Australian Energy Market Operator’s March 2018 Victorian Gas Planning Report highlights a potential shortfall in gas supply during peak gas demand in 2021 and a potential shortfall in total supply in 2022. Remediation work needs to start now so that, should AGL obtain the required project approvals and make the decision to proceed, Berth No.2 is available in time to meet this forecast shortfall.”

Mr Geier noted that the Port was fortunate to be in a position to be able to assist AGL in securing Victoria’s gas supply needs. “The Port is well placed with natural deep water channels and existing infrastructure available to facilitate projects such as AGL’s.  The prospect of the Port playing a part in AGL’s plans to secure the State’s gas supply needs and provide additional competition in the domestic market is exciting.”


26/04/2018  - Crib Point Jetty Remediation

The Port of Hastings Development Authority is preparing to commence remediation works on Berth 2 at the southern end of the Crib Point Jetty.  The work is being undertaken now to ensure Berth 2 is ready in time for the AGL Gas Import Jetty project, should the project proceed.  If AGL does not proceed with the project, Berth 2 will be available for use by other port users.

Residents and users of Western Port can expect to see remediation activity on the jetty site commencing May 2018.

Works at the site will include:

  • Establishment of a site compound;

  • Securing the site with new fencing;

  • Some vegetation clearing;

  • Repairs to concrete on the jetty, pylons, mooring dolphins and pipe racks; and 

  • Replacement of the Pier head.

Residents can expect to see an increase in  vehicle movements along The Esplanade during these works.  Construction activities will occur between:

  • Monday to Friday - 7am to 6pm; and

  • Saturday - 7am to 1pm.                       

The Port of Hastings Development Authority’s works are expected to take between 7 and 9 months, commencing in May 2018 and ending in January 2019. 

For more information on the Berth 2 remediation works please contact our office on 5979 5500 or visit www.portofhastings.com.

For information on the AGL Gas Import project please contact Jay Gleeson, AGL Community Relations Manager on 0499 027 630 or visit www.agl.com.au/cribpoint.

 


02/11/17 - Port of Hastings deploys innovative new Sealite buoy in Western Port

Sealite's new Atlantic 3000 ocean buoy is the first large ocean buoy in its class to offer a 3 metre diameter float section without the incorporation of a central steel mooring post. This innovative modular design ensures the buoy is fast, safe plus easy to assemble and deploy.


10/08/2017 - The Port of Hastings Development Authority welcomes the announcement by AGL that the Port's jetty located at Crib Point in Western Port is the preferred location for AGL's gas import jetty. This project will help secure the states gas supply needs and bring competition to the domestic market.